Hershey Public Schools is currently renovating the south area of the building along with the old gym area. Five remodeled elementary classrooms will be renovated. All of these classrooms will be increased from 525 square feet to well over 900 square feet. New ADA bathrooms, administrative offices and a safe and secure entrance are being constructed in this space as well.
The old gym area is being renovated to become a new K-12 Media center, SPED classrooms, Guidance Counselor offices and a collaboration space. Both of these areas are expected to be available to utilize in the fall with students!
Picture of secretary/reception area of office. This space was occupied by the old junior high girls locker room. Looking north into the new media center.
Picture of secretary/reception office looking to the west.
Hallway of administrative offices, looking west.
ADA bathroom tile is being installed.
One of five elementary classrooms.
K-12 Media Center looking north
K-12 Media Center looking to the west.
Picture of the hallway which was extended through the stairwell. Looking to the west.
Picture of concrete poured for the hallway, left is media center and to the right of the hallway will be the administrative offices. Picture taken from the south stage stairwell.
South stage stairwell prior to demolition.
South stage stairwell, without the stairs. Looking north to the collaboration space (stage floor). Glass windows and doors will be located where the stage curtains were hanging.
Entrance into the bathrooms, prior to the demolition of the stairs.
Dirt work, getting prepared for the footings to go in.